Interactive question walkthrough

The Dinosaur Has a Deadline: PERT and Three-Point Estimating

The museum doors open tonight. Use PERT to turn three uncertain estimates into one expected duration, then move the sliders and watch the numbers change.

PERT and three-point estimating

A natural-history museum must complete the final mount of its Tyrannosaurus rex skeleton before opening night. The installation team estimates 6 days under optimistic conditions, 10 days as the most likely duration, and 20 days under pessimistic conditions. Using PERT, what expected duration should the project manager use for the activity?

Choose a duration to continue.