Estimating tool
PERT Three-Point Estimating Calculator
Calculate a weighted expected duration from optimistic, most-likely, and pessimistic estimates.
Museum estimate lab
Move three estimates. Watch the weighted answer shift.
Try a preset or adjust the three estimates.
Three-point estimate
The controls preserve O ≤ M ≤ P. Values represent days for one uncertain activity.
Live estimate
Enable JavaScript to update the estimate.
Important: PERT is an estimating model, not a promise. Its usefulness depends on realistic inputs and sound schedule logic.
For the worked example and reasoning, read the related study guide.
How it works
Provide optimistic, most-likely, and pessimistic durations. PERT gives the most-likely estimate four times the weight of either outer estimate.
Example to try
With 6 optimistic days, 10 most-likely days, and 20 pessimistic days, the weighted estimate is 11 days while the ordinary average is 12 days.
Read the result
The expected duration is an estimate rather than a promised deadline. Standard deviation and variance describe the spread between the optimistic and pessimistic cases.